I didn't make it out there for week 3 and a little late for this update. Work has been busy.
The water,sewerage and drainage system is starting to be put into place. the layout and the grading for the road course has started and the frame work for the foundation the first set bleachers to be moved to the east side of the drag strip is in place. Just need no rain to pour the concrete. Next update will be for week 6. I will not get out there this week.
Ed
The water,sewerage and drainage system is starting to be put into place. the layout and the grading for the road course has started and the frame work for the foundation the first set bleachers to be moved to the east side of the drag strip is in place. Just need no rain to pour the concrete. Next update will be for week 6. I will not get out there this week.
Ed