68 C3 updates
The car was built to perform on and off track, with AC, power steering - a pump gas cruiser.
Since completion I have put about 2,000 miles on the car and have ran the Texas mile 3 times with a best speed of 194.7 mph and a best 1/4 mile ET of 9.70. Needless to say, I have been very pleased with the outcome of this effort.
The car is now tuned for E85 and we installed a nitrous system in the intake manifold. The speed/et stated above were motor only figures, the nitrous was not added at this time. We had the car on the dyno earlier this year and made 730 rwhp on motor and 915 rwhp with the nitrous shot.
Late March we were registered to participate in the Texas mile event. We teched the car in on Thursday to begin passes on Friday morning. I made two “shake down” passes Friday morning in the 192 mph range. The weather was to change on Saturday, so Friday afternoon was probably going to be our best run of the event. I reviewed the data from the last two runs to confirm that AFR, timing, shift points, etc., were good and loaded the “moon tune” to potentially break the illusive 200 mph mark. After about 2 1/2 hours of making our way through the starting grid, it’s go time. There is a final safety check prior to moving to the starting line and an opportunity for a very short burnout. I passed safety and engaged the line lock for the burnout. As the tires began to spin, I heard what I believed to be a bottom end knock in the engine. I tapped the throttle again to confirm and I was unfortunately correct. I aborted the run and drove back to our pit area. We removed the valve covers to eliminate a valve train issue. No suck luck and back on the trailer.
After removing the oil pan it was obvious that we had a bearing issue. #6 rod bearing had failed, which also took out #5. The crankshaft was damaged beyond repair and #6 rod had some damage, but beyond that all seemed good. We completely disassembled the motor and inspected all components. All still appeared to be fine. I somehow remembered that BPE has a 3 yr warranty. I found my original purchase paperwork from BPE and had 11 days remaining on my warranty. I contacted BPE and they began a claim. The following day a warranty specialist contacted me and we discussed the issues. He immediately offered to ship the motor back to BPE and completely rebuild at their expense. In lieu of this I requested to have the components sent to me directly and we would rebuild the motor. This was for 2 reasons, one, I wanted to control the build and two, we wanted to make some changes also. With 7 days BPE furnished a new crankshaft, rods, rings, bearings, gaskets, timing chain and gears. Probably missing a few items, but these are truly first class people at BPE!
We wanted to bump the compression to about 12.25 to 12.5:1 (safe on E85), and go to a solid roller camshaft to allow for around 7,800 rpm shifts. Currently the camshaft has been ground, diamond pistons have arrived, rotating assembly is now balanced and short block is built. While the heads were off, we polished the runners and combustion chambers and port matched the heads to the intake. New valves, springs and retainers were installed. We are waiting on the lifters, which are scheduled to arrive on Tuesday, to complete the engine.
It’s been almost a 3 month process and I am getting pretty anxious. The engine builder feels like we will see gains of between 100 and 150 rwhp. Hopefully we will have the car on the dyno some time in July. Fingers crossed!
Should have the motor back from the machine shop next week.
The Best of Corvette for Corvette Enthusiasts




















